The first phase of the airport will be able to handle 20 million passengers per annum. It will be expanded to its final capacity to handle more than 90 million passengers per annum. Texas-based Jacobs Engineering Group will chart the final masterplan for the airport,while the airport passenger terminal and air traffic control (ATC) tower will be designed by London-based Zaha Hadid Architects.
The airport covers an area of 1,160 hectares (4.5 sq mi).
The Navi Mumbai International Airport is expected to be fully operational in 2023 at the latest.
Contents
- History
- Facilities
- Structure
- Runways
- Terminal
- Cargo terminal
- Other facilities
- Airport plans
- See also
- References
- External links
History
The project was first conceived in November 1997 when the Ministry of Civil Aviation (MoCA) constituted a committee to examine various sites for a second airport for Mumbai. The committee recommended a site at Mandwa–Rewas in June 2000, since the proposed airport was to have a single runway. That September, CIDCO revised the original proposal to provide for a pair of parallel runways and submitted its feasibility report to the MoCA. AAI’s sub-committee found the Navi Mumbai site technically and operationally feasible, and suggested that CIDCO carry out a detailed Techno Economic Feasibility Study (TEFS) of the project. The TEFS was submitted in 2001 following which the International Civil Aviation Organization (ICAO) conducted a simulation study which confirmed that simultaneous operation of two airports was possible with appropriate procedures in place. In February 2007, CIDCO submitted a Project Feasibility and Business Plan Report to the MoCA, and the project received in-principle approval from the Union Cabinet in July.
In July 2008, the Government of Maharashtra granted approval for development of the project on a PPP basis and appointed CIDCO as the nodal agency for its implementation. The project received defence clearance by the Ministry of Defence (MoD) by the end of 2010. The site had several environmental problems in dealing with mangroves and rain/storm water drains in Panvel. There is an NGO fighting government agencies regarding Panvel. The Ministry of Environment and Forests (MoEF) gave its clearance for the Navi Mumbai international airport on 14 May 2008.The environmental ministry finally cleared the project on 23 November 2010.
CIDCO invited global tenders for requests for qualification (RFQ) on 5 February 2014. The agency received nine bids and shortlisted four bidders, including GMR Group, the GVK-led MIAL, Hiranandani Developers, Zurich Airport and Mia Infrastructure with Tata Realty and Infrastructure. It submitted their RFQs to the project management committee (PMC) for scrutiny. The PMC will then submit its report to the Maharashtra Chief Minister who must approve the project, before it receives final approval from the Ministry of Civil Aviation. GVK was the only bidder in the final two rounds of bidding, causing CIDCO to extend the deadline for the tender twice. Subsequently, the GMR Group submitted a bid. On 13 February 2017, GVK-led MIAL was announced as the winning bidder. GVK offered CIDCO a 12.6% share in revenue compared to the 10.44% offered by the GMR Group.
The Union Ministry of Environment, Forests and Climate Change provided clearance to carry out pre-development work for the airport in April 2017. However, work could not begin until 14 June 2017 due to opposition from local villagers. Pre-development work includes flattening the Ulwe hill, reclaiming marsh land, diverting the Ulwe river outside the airport boundary and widening the channel to 60 metres, and shifting power transmission lines. It is expected to take two years to complete. CIDCO will raise the level of the land by 5.5 metres. Work was stalled again from 12 October due to protests from local villagers, but resumed on 28 October 2017 after CIDCO reached an agreement with the protestors.
Prime Minister Narendra Modi unveiled the foundation plaque at the ground breaking ceremony for the Navi Mumbai International airport in Mumbai on 18 February 2018. The GVK led Navi Mumbai International Airport (P) Limited (NMIAL), appointed Zaha Hadid Architects (ZHA) in March 2018 to design the Navi Mumbai International Airport’s Terminal 1 and ATC Tower. The London-based ZHA was selected on completion of a 12-week fast track design competition amongst the international architecture firms that were shortlisted by GVK. CIDCO floated a tender to select the engineering, procurement, and construction contractor for the project in August 2018.
CIDCO had appointed Pune based Central Water and Power Research Station(CWPRS) in 2011 to study the hydrological impact of the airport on the surrounding waterbodies. The CWPRS conducted hydrological and Mathematical Model studies of the Ulwe river catchment area and had recommended cutting a channel to divert the Ulwe river into the Moha creek. CIDCO completed pre-development work on the Ulwe river diversion by June 2019.
In September 2019, GVK awarded a contract for construction of the airport to L&T Engineering and Construction.
Facilities
Structure
The airport will have an apron area of 67,000 m2 (720,000 sq ft), 17,000 m2(180,000 sq ft) terminal area, and parking for ten code C aircraft.
Runways
The airport will have two runways:
- Runway 08L/26R: 3,700 by 60 metres (12,140 ft × 200 ft)
- Runway 08R/26L: 3,700 by 60 metres (12,140 ft × 200 ft)
Terminal
The terminal building will be spread over 523,000 m2 (5,630,000 sq ft) capable of handling 60 million passengers per annum (MPPA). The terminal will have 78 contact airport positions and 29 remote aircraft positions. There will be more than 350 check-in counters.
The airport will also have a low cost carrier terminal capable of handling two million passengers per annum in the first phase.
Cargo terminal
The domestic cargo terminal will be spread over 33,000 m2 (360,000 sq ft) and the international cargo terminal will be spread over 23,700 m2(255,000 sq ft).
Other facilities
The airport will have a 151,000 m2 (1,630,000 sq ft) fuel farm and three aircraft hangars.
Airport plans
The coastal land required is about 2,900 ha (7,200 acres) with 1,320 ha (3,300 acres) for the core airport activity and another 245 ha (610 acres) on Waghivali Island to be developed as Mangrove Park and will have two parallel runways each 3,700 m (12,139 ft) long. It is to be located on National Highway 4Bnear Panvel, about 35 km (22 mi) from the existing Chhatrapati Shivaji Maharaj International Airport.
The airport will have a terminal area of 250,000 m2 (2,700,000 sq ft) and a cargo area of 100,000 m2 (1,100,000 sq ft) and handle 50–55 million passengers annually. The site of airport is located in an area of 9.5 km2(3.7 sq mi)
The original estimated cost of the project was ₹47.66 billion (US$670 million). This has since quadrupled to ₹160 billion (US$2.2 billion). CIDCO’s RFQ in 2014 estimated total project cost for the development of phase 1 and 2 of NMIA to be ₹95 billion (US$1.3 billion). The cost of pre-development work was estimated at ₹23.58 billion (US$330 million), which including ₹15.38 billion(US$220 million) of land development for airport and ₹8 billion (US$110 million) for other works.
The project required the relocation of 2,786 households located across 10 villages—Chinchpada, Kopar, Kolhi, Ulwe, Upper Owale, Waghivalivada, Vaghivali, Ganeshpuri, Targhar, and Kombadbhuje. Most of the residents affected by the project are fishermen, farmers, or work odd jobs. CIDCO compensated land owners paying ₹1,500 (US$21) per sq ft of the land, rent for 18 months, and a developed plot of land of a size equal to triple the roof area with 1.5 FSI in the Pushpaknagar node. CIDCO extended the deadline for all residents to vacate their houses to 30 November 2018, and again to 15 January 2019.
The airport was expected to open in 2019. The deadline was extended by Devendra Fadnavis the Chief Minister of Maharashtra, due to multiple delays in obtaining clearances for the commencement of the construction work.Civil Aviation Secretary R.N. Choubey stated in September 2018 that the first flight from Navi Mumbai International Airport was expected to begin operating by September 2021.